Second Street LINK Transit Construction

 Impact Lvl 1: Governance/Public Policy ; Transportation
Lvl 2: Heart of the City Discovery Square
Public Report on LINK - Bus Rapid Transit led by Mayo, City of Rochester, DMC
Last modified: September 19, 2025

Contents

Highlights


City, DMC PSA: 

  • Beginning September 22, traffic on 2nd Street SW will shift to maintain one lane in each direction between 18th Avenue SW and 23rd Avenue SW.
  • Affected areas

Contents


Second Street Construction PSA

 

 

Back to TOC

 


 

Maps

 

3rd Ave SE Closure

 

 

Back to TOC

 


 

19th Ave SW

 

 

Back to TOC

 


 

2nd St SW at 23rd Ave SW

 

 

Back to TOC

 


 

 


 

 

  

 

Related Reports


 

Other LINK - Bus Rapid Transit Pinned Reports



August 08, 2025 : LINK - Bus Rapid Transit New Budget Increase

  • DMCC Special Board Meeting July 22, 2025 Approving Budget Increase
  • City Council July 20, 2025 New Budget Increase: A nearly $73.2 million contract for construction of key elements of Rochester’s Link Bus Rapid Transit project is spurring a call for added transit aid.
  • 2025-08-08 Updated to include PB articles
Impact Lvl1: Transportation
Impact Lvl2:



March 28, 2025 : Link BRT a milestone project for Rochester

DMC Feb 2025 Board Meeting Memo 

City of Rochester Receives $84.92 Million Federal Grant for Transformative Link Bus Rapid Transit Project

LINK Progress Report to City Council 

Rochester eyes TIF to support Transit Village, Public Parking

March & May, 2025 Update per PB Reporting

Impact Lvl1: Governance/Public Policy, Housing, Transportation
Impact Lvl2: Housing: Affordable Rate, Housing: Market Rate



December 08, 2023 : Mobility Updates

October 23, 2023 City Council Study Session 

May 2022; February 2022 and November 2021 Rapid Transit Updates and Upcoming milestones presented to DMCC. 

Impact Lvl1: Transportation
Impact Lvl2:



November 20, 2020 : DMC Transportation Plan - Circular

DMCC Board Voted in favor of staff recommendations 2019

Impact Lvl1: Health, Sustainability, Transportation
Impact Lvl2:



September 08, 2020 : Rochester City Transit Development Seeking Co-designers

Co-designers will be Rochester residents with strong connections to their communities and local knowledge of their neighborhood and the Rapid Transit Project area. 

Impact Lvl1: Best Practice, Co-design, Diversity and Inclusion, Transportation
Impact Lvl2:



September 26, 2019 : Destination Medical Center Corporation Board Green Lights Mobility Hub Locations in Rochester

September, May and Feb 2019 Presentations to DMCC. 

Impact Lvl1: Transportation
Impact Lvl2:


Back To Top

 

Pinned Mayo, City of Rochester, DMC organization and project reports


.
Project Report of LINK - Bus Rapid Transit : August 08, 2025 : LINK - Bus Rapid Transit New Budget Increase

  • DMCC Special Board Meeting July 22, 2025 Approving Budget Increase
  • City Council July 20, 2025 New Budget Increase: A nearly $73.2 million contract for construction of key elements of Rochester’s Link Bus Rapid Transit project is spurring a call for added transit aid.
  • 2025-08-08 Updated to include PB articles
Impact Lvl1: Transportation
Impact Lvl2:



Project Report of West Transit Village : May 24, 2025 : West Transit Village DMC Board Meeting

May 2025 DMCC Board Meeting Report

Feb 2025 DMCC Board Meeting Memo

PB reporting re Jan 6 City Council Meeting

"A final plan for dividing a 14.1-acre Mayo Clinic parking lot into developable sections is expected to be reviewed Monday by the Rochester City Council. The site, being dubbed “West Transit Village,” sits between Second Street Southwest and Cascade Lake. It is currently used as a Mayo Clinic employee shuttle lot, and Mayo Clinic plans to construct a 2,500-stall parking structure."

Impact Lvl1: Economic Development, Housing, Recreation & Open Space, Transportation
Impact Lvl2:



Project Report of LINK - Bus Rapid Transit : March 28, 2025 : Link BRT a milestone project for Rochester

DMC Feb 2025 Board Meeting Memo 

City of Rochester Receives $84.92 Million Federal Grant for Transformative Link Bus Rapid Transit Project

LINK Progress Report to City Council 

Rochester eyes TIF to support Transit Village, Public Parking

March & May, 2025 Update per PB Reporting

Impact Lvl1: Governance/Public Policy, Housing, Transportation
Impact Lvl2: Housing: Affordable Rate, Housing: Market Rate



Project Report of West Transit Village : September 30, 2024 : West Transit Village

September 2024 DMCC Board Update

September 2022 DMCC Board Status: NTH to run a developer selection process with Mayo

 

Impact Lvl1: Economic Development, Housing, Recreation & Open Space
Impact Lvl2: Economic Diversification, Housing: Affordable Rate, Housing: Market Rate, Transportation



Project Report of LINK - Bus Rapid Transit : December 08, 2023 : Mobility Updates

October 23, 2023 City Council Study Session 

May 2022; February 2022 and November 2021 Rapid Transit Updates and Upcoming milestones presented to DMCC. 

Impact Lvl1: Transportation
Impact Lvl2:



Project Report of LINK - Bus Rapid Transit : November 20, 2020 : DMC Transportation Plan - Circular

DMCC Board Voted in favor of staff recommendations 2019

Impact Lvl1: Health, Sustainability, Transportation
Impact Lvl2:



Project Report of LINK - Bus Rapid Transit : September 08, 2020 : Rochester City Transit Development Seeking Co-designers

Co-designers will be Rochester residents with strong connections to their communities and local knowledge of their neighborhood and the Rapid Transit Project area. 

Impact Lvl1: Best Practice, Co-design, Diversity and Inclusion, Transportation
Impact Lvl2:


Back To Top

 

Projects & News
Anchor Projects

Anchor projects provide the backdrop of our community's major initiatives and have overarching impacts to the community:

Latest Pin Reports

Noteworthy community status reports:




Search more Pin Beam Reports

Site Information
About Beam
  • For the commercial sector, we tend to register startup activities (new companies and new commercial projects) that bring diversification and high-impact opportunities to the area.
  • For the non-profit sector, we wish to shine light on all the organizations and services that otherwise labor under relative obscurity.
  • Our hope is that dmcbeam.org will encourage cross-sector collaborations and creative solutions.

While there are a number of registries in the community, dmcbeam.org's  distinct value is to pilot a database with a data structure and categorizations that answer the questions such as: What organizations or projects/programs in our community that have purported relevance with some of the over-arching focuses put forward by initiatives such as DMC, J2G and Health Improvements?

This database could be used as one of the ways to explore the capacities of the community. If you are someone on an exploratory journey to learn about the greater Rochester community. dmcbeam.org could be an interesting first step.

Project Phase Definitions
The following defines the various project phases:
  1. Available - a product, program or service is in production
  2. Develop - program or application is being developed
  3. Plan - idea is solid, stakeholders are identified, and there is strong commitment to go forward from all parties.
  4. Concept Phase - idea scoped out with enough details to give an early sizing and/or to build a proof of concept